Civil Engineering Objective Questions { PERT and CPM }



50. The critical activity has
A. maximum float
B. minimum float
C. zero float
D. none of these.
Discuss in Forum

51. The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as
A. duration
B. total flat
C. free float
D. interfering float.
Discuss in Forum

52. For completion of a project, the critical path of the network represents
A. minimum time
B. maximum time
C. maximum cost
D. minimum cost.
Discuss in Forum

53. Which one of the following represents an activity
A. excavation for foundation
B. curing of concrete
C. setting of question paper
D. all the above.
Discuss in Forum

54. Which one of the following represents an event ?
A. concrete cured
B. fixing of door
C. plastering of walls
D. selecting sites
Discuss in Forum

55. Pick up the correct network for the activities of pouring concrete, erection of form work, removal of form work and curing of concrete from the following :
A. 1. Pouring of Concrete,2. Erection of form work,3. Curing of concrete,4. Removal of form work
B. 1. Erection of form work ,2. Pouring of concrete3. Curing of concrete,4. Removal of form work
C. 1. Removal of form work 2. Erection of form work3. Pouring of concrete,4. Curing of concrete
D. 1. Pouring of concrete2. Curing of concrete 3. Erection of form work 4. Removal of form work.
Discuss in Forum

56.  In a certain project an activity C can only be started when activities A and B have been completed, which have no bearing on each other and can be started independently. The correct network for the activities, is
A. Activities A and B can be started independently
B. Activity C can be started only on completion of activity A
C. Activity D can be started only on completion of activity
D. all the above
Discuss in Forum