Login
Signup
Engineering
MECHANICAL ENGINEERING
ELECTRICAL ENGINEERING
ELECTRONICS ENGINEERING
CIVIL ENGINEERING
CHEMICAL ENGINEERING
AUTOMOBILE ENGINEERING
Aptitude
QUANTITATIVE APTITUDE
VERBAL ABILITY
GS
GENERAL KNOWLEDGE
CURRENT AFFAIRS
More
COURSE ON COMPUTER CONCEPTS
MICROBIOLOGY
BIOCHEMICAL ENGINEERING
BIOTECHNOLOGY
BIOCHEMISTRY
TECHNICAL MCQs
STATE GOVERNMENT EXAMS
Civil Engineering Objective Questions
{ PERT and CPM }
Home
//
Civil Engineering
// PERT and CPM
92. Pick up the correct statement from the following :
A. The early start time of an activity is the maximum of the early finish times of all its immediate predecessors
B. The sequence of the activities on the longest path in the network, is the project's critical path
C. The procedure of finding the early start and early finish times of each of the begining activities, then those of their successors, their successors' successors, and so on is called the forward pass through the network
D. All the above
View Answer
Discuss in Forum
93. Pick up the correct statement from the following :
A. Total slack is the difference between its late start and early start times
B. Total slack is the difference between its late finish and early finish times
C. The activities on the critical path have zero total slack
D. All the above.