22. The area is measured correct to the nearest
A. 0.01 sqm
B. 0.02 sqm
C. 0.03 sqm
D. 0.04 sqm

23. The volume is measured correct to the nearest
A. 0.01 cum
B. 0.02 cum
C. 0.03 cum
D. 0.04 cum

24. The weight of an item is measured correct to nearest
A. 0.25 kg
B. 0.50 kg
C. 0.75 kg
D. 1.00 kg

25.  Pick up the correct statement from the folio ng
A. Bricks are paid per thousand
B. Cement is paid per 50 kg bag
C. Lime is paid per quintal
D. All the above.

26. While preparing a detailed estimate
A. Dimension should be measured correct to 0.01 m
B. Area should be measured correct to 0.01 sqm
C. Volume should be measured correct to 0.01cum
D. All the above.

27.  Pick up the correct statement regarding the centre line method of estimating a building
A. Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item
B. The centre line is worked out separately for different sections of walls of a building
C. The centre line length is reduced by half the layer of main wall joining the partition wall
D. All the above.

28. The 'centre line method' i specially adopted for estimating
A. Circular buildings
B. Hexagonal buildings
C. Octagonal buildings
D. All the above.