92. The item of steel work which is measured in sq. m, is
A. Collapsible gates
B. Rolling shutters
C. Steel doors
D. All the above.
93. Pick up the correct statement from the following :
A. Pointing is measured in sq. m
B. Plastering is measured in sq. m
C. Glazing is measured in sq. m
D. All the above.
94. For 12 mm thick cement plastering 1 : 6 on 100 sq. in new brick work, the quantity of cement required, is
A. 0.200 m3
B. 0.247 m3
C. 0.274 m3
D. 0.295 m3.
95. For 100 sq. m cement concrete (1 : 2 : 4) 4 cm thick floor, the quantity of cement required, is
A. 0.90 rn3
B. 0.94 m3
C. 0.98 m3
D. 1.00 m3.