190. When drainage to sewage ratio is 20, the peak dry weather flow is
A. 20% of the design discharge
B. slightly less than 5% of the design discharge
C. slightly more than 5% of the design discharge
D. none of these.
191. Sewer pipes need be checked for
A. minimum flow
B. maximum flow
C. both A and B
D. none of these.
192. The design period of sewage treatment works in normally
A. 5-10 years
B. 15-20 years
C. 30-40 years
D. 40-50 years.
193. For sewer mains of 0.5 to 1 m diameter, the ratio of maximum daily sewage flow to the average daily sewage flow is assumed
A.1.5
B.2
C.2.5
D. 3.0.
194. For trunk sewers more than 1.25 m in diameter, the ratio of the maximum daily sewage flow to the average daily sewage flow is assumed
A.1.5
B.2
C.25
D.3
195. The ratio of minimum hourly flow to the average flow of sewage is
A. 1/4
B. 1/3
C. 1/2
D. 3/4.
196. Sewer pipes are designed for maximum discharge with 25% to 33% vacant cross-sectional area for
A. unexpected large scale infiltration of stream water
B. unexpected increase in the population
C. under estimates of maximum and average flows
D. All of the above.