169. The digested sludge from septic tanks, is removed after a maximum period of
A. 3 years
B. 3.5 years
C. 4 years
D. 5 years.
Discuss in Forum

170.  The rate of accumulation of sludge per person per year, is
A. 10 litres
B. 15 litres
C.c) 20 litres
D. 25 litres
Discuss in Forum

171. In septic tanks,
A. free board of 0.3 m may be provided
B. the baffles or tees are extended up to top level of scum
C. the clear-space between the baffle top and covering slab is about 7.5 cm
D. all the above.
Discuss in Forum

172.  The bottom of the sewage inlet chamber of septic tanks, is provided an outward slope
A. 1 in 5
B. 1 in 10
C. 1 in 15
D. 1 in 20
Discuss in Forum

173.  Bottom openings 15 cm x 15 cm in the standing baffle wall are provided
A. 15 cm c/c
B. 22.5 cm c/c
C. 30 cm c/c
D. 50 cm c/c.
Discuss in Forum

174. In a septic tank of de-sludging period of 1 year, receives sewage for 100 persons @ 120 litres per person per day. If the depth is kept 1.667 m and length-width ratio is 4, the length and width of the septic tank, are :
A. 4 and 1 m
B. 4.80 m and 1.20 m
C. 5.20 m and 1.30 m
D. 6.00 m and 1.50 m.
Discuss in Forum

175.  In case of Imhoff tanks,
A. the shape is rectangular
B. detention period is 2 hours
C. the velocity of flow is restricted to 0.30 m/minute
D. All the above.
Discuss in Forum